# APPENDIX 1 Key



> 原始法庭文件为英文；下方为英文全文，顶部为中文摘要。

## **APPENDIX 1**

## Key

## COLUMN LABEL - DESCRIPTION

The original estimates collectively forecast a work period after haul-out of 45 with the best effort and a Class 5 Risk factor of 100% due to lack of details ORIGINAL

Assumes delays due to additional parts needed up to 90 days EXTENDED 1

Assumes delays and additional parts needed and new work on the Port Diesel Engine up to 135 days EXTENDED 2

Assumes delays and additional parts needed and new work to replace both Diesel Engines up to 150 days EXTENDED 3

| ITEM | DESCRIPTION                                             | ITEM COST |         | ORIGINAL      | 45<br>DAYS |  |    | EXTENDED 1   | 90<br>DAYS | EXTENDED 2 |    | 135<br>DAYS  | EXTENDED 3 | 150<br>DAYS |     |
|------|---------------------------------------------------------|-----------|---------|---------------|------------|--|----|--------------|------------|------------|----|--------------|------------|-------------|-----|
| 1    | DRY DOCK OR HAUL-OUT FOR REPAIRS                        | \$        | 25,000  | \$<br>25,000  | 2          |  | \$ | 25,000       | 2          |            | \$ | 25,000       | 2          | \$ 25,000   | 2   |
| 2    | LAYDAYS ON LAND STORAGE                                 | \$        | 20,385  | \$<br>20,385  | 45         |  | \$ | 40,770       | 90         |            | \$ | 61,155       | 135        | \$ 81,540   | 150 |
| 3    | ENGINE ROOM RIPOUT OF INTERFERENCES FOR<br>ACCESS       | \$        | 129,000 | \$<br>129,000 | 14         |  | \$ | 129,000      | 14         |            | \$ | 258,000      | 14         | \$ 258,000  | 14  |
| 4    | ENGINE TAKE DOWN                                        | \$        | 72,000  | \$<br>72,000  | 7          |  | \$ | 72,000       | 7          |            | \$ | 72,000       | 7          | \$ 72,000   | 7   |
| 5    | ENGINE UNFORESEEN REPLACEMENT PARTS                     | \$        | 30,000  | NA            |            |  | \$ | 30,000       | 7          |            | \$ | 30,000       | 7          | \$<br>3,000 | 7   |
| 6    | ENGINE REASSEMBLY                                       | \$        | 77,000  | \$<br>77,000  | 7          |  | \$ | 77,000       | 7          |            | \$ | 77,000       | 7          | \$ 77,000   | 7   |
| 7    | ENGINE TO SHAFT ALIGNMENT                               | \$        | 10,000  | \$<br>10,000  | 3          |  | \$ | 10,000       | 3          |            | \$ | 10,000       | 3          | \$ 10,000   | 3   |
| 8    | ENGINE ROOM INSTALLATION OF INTERFERENCES               | \$        | 129,000 | \$<br>129,000 | 14         |  | \$ | 129,000      | 14         |            | \$ | 258,000      | 14         | \$ 258,000  | 14  |
| 9    | HULL VALVE REMOVAL                                      | \$        | 50,000  | \$<br>50,000  | 14         |  | \$ | 50,000       | 14         |            | \$ | 50,000       | 14         | \$ 50,000   | 14  |
| 10   | HULL VALVE TEST                                         | \$        | 50,000  | \$<br>50,000  | 14         |  | \$ | 50,000       | 14         |            | \$ | 50,000       | 14         | \$ 50,000   | 14  |
| 11   | HULL VALVE UNFORESEEN REPLACEMENT PARTS                 | \$        | 20,000  | NA            |            |  | \$ | 20,000       | 14         |            | \$ | 20,000       | 14         | \$ 20,000   | 14  |
| 12   | HULL VALVE REINSTALLATION                               | \$        | 60,000  | \$<br>60,000  | 14         |  | \$ | 60,000       | 14         |            | \$ | 60,000       | 14         | \$ 60,000   | 14  |
| 13   | HULL PAINTING                                           | \$        | 9,000   | \$<br>9,000   | 7          |  | \$ | 9,000        | 7          |            | \$ | 9,000        | 7          | \$<br>9,000 | 7   |
| 14   | DECK REPAIR                                             | \$        | 3,000   | \$<br>3,000   | 7          |  | \$ | 3,000        | 7          |            | \$ | 3,000        | 7          | \$<br>3,000 | 7   |
| 16   | PORT ENGINE FUEL PUMP INSPECTION                        | \$        | 9,000   | NA            |            |  | \$ | 9,000        | 7          |            | \$ | 9,000        | 7          | \$<br>9,000 | 7   |
| 17   | PORT ENGINE REPAIR                                      | \$        | 447,000 | NA            |            |  |    | NA           |            |            | \$ | 447,000      | 30         | \$ 140,000  | 30  |
| 18   | ABS OR LLOYDS SOCIETY HULL AND SHAFT CERT               | \$        | 5,000   | \$<br>5,000   | 3          |  | \$ | 5,000        | 3          |            | \$ | 5,000        | 3          | \$<br>5,000 | 3   |
| 19   | CREW RETENTION                                          | \$        | 50,000  | \$<br>50,000  | 45         |  | \$ | 100,000      | 90         |            | \$ | 150,000      | 135        | \$ 200,000  | 150 |
| 20   | NEW DIESEL ENGINES                                      | \$        | 550,000 | NA            |            |  |    | NA           |            |            |    | NA           |            | \$ 550,000  |     |
| 21   | SUBTOTAL                                                |           |         | \$<br>689,385 |            |  | \$ | 818,770      |            |            |    | \$ 1,594,155 |            | \$1,880,540 |     |
| 22   | RISK OF DELAY OF NEW PARTS AND AVAILABLE<br>TECHNICIANS |           |         | \$<br>689,385 |            |  | \$ | 818,770      |            |            |    | \$ 1,594,155 |            | \$1,880,540 |     |
| 23   | GRAND TOTAL                                             |           |         | \$ 1,378,770  |            |  |    | \$ 1,637,540 |            |            |    | \$ 3,188,310 |            | \$3,761,080 |     |