## **EXHIBIT PAX 05**
Exhibit D to Repair Reserve Motion (Safe Harbor Newport Shipyard Estimate)
## **EXHIBIT D**

Estimate #
Customer Name: Patrick McLister - Captain
Vessel Name: MY - Lady May
Phone: 954-701-1097
Email: captain@yachtladymay.com
Date: 7/20/2022
Estimate Description:
Removal of Through Hull Valves - Cleaning and Testing
Painting - Re-installation - Hydro Testing
Comments or Special Instructions:
## SCOPE OF WORK:
Removal of through hull butterfly / ball and globe & gate valves. Cleaning of flanges and valves. Bench testing with report
Assuming all parts are in good working and no need to supply new valves
| DESCRIPTION | QTY | AMOUNT (\$) | |----------------------------------------------------------------------------------------------|--------|-------------| | Labor to remove approximately 26 valves - clean - re-furbish - test and installation | | | | - 1.5 work week to remove - 1.5 work week to clean and test - 1.5 week in re-install | | \$59,500.00 | | This estimate is based on documentation provided by the Yacht and not by any inspection | | | | by either the sub-contractor or the Shipyard. The final cost maybe greater or less than this | | | | Estimate. It is not ment to be binding to either party | | | | | | | | | | | | | | | | | | | | | TOTAL: | \$59,500.00 |
The estimated prices are given for budgetary purposes only and are not to be considered as binding. This estimate is valid for 14 days from receipt. Invoices are subject to the 5% Environmental Fee and 7% RI Sales Tax where applicable. \*\*15% Subcontractor Commision due for any subcontractors you are working directly with. A carbon copy of the Subcontractor's Invoice must be provided.\*\*
• Any Repairs/rebuilds – Additional repairs and/or replacements are not included and will be addressed separately upon discovery as/if needed
• Any task that may need crane or forklift - Crane and forklift charges are not included and will be billed separately on the shipyard services tasks on a T&M basis as needed.
Approved: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_