Lady May - Bridgeport Boat Works(BBW) - 2022

#

Total BBW Shipyard Estimates Total BBW Shipyard Actual

#
and Quotes \$529,958.79 Cost \$0.00
#

Job Description Company Estimate Quote Actual Notes Engineering Total \$422,961.35 \$0.00 \$0.00

#
Support of Ring Power repairs to stbd main
#

engine. Hornblower \$290,047.72 Protection, building required A-frames, removing and re-installing parts of the engine room as required, etc. Estimate is \$272,729.40. Estimated sales tax would be \$17,318.32.

#
Repair of starboard main
#

engine. Ring Power \$99,777.10 Estimate is \$93,819.56. Estimated sales tax would be \$5,957.54.

#
Service of port and
#

starboard main engines. Ring Power \$33,136.53 Service both main engines after repairs to the stbd main engine are completed. Estimate of \$15,579.00 per engine. Estimated sales tax would be \$1,978.53.

#
Dockage and Yard
#

Services - 60 days Total \$79,757.19 \$0.00 \$0.00 Shore Power \$7,912.20 \$124.00/day. Estimated sales tax would be \$7.87/day. Black/grey water tank \$532.81 \$501 flat fee estimate. Estimated sales tax would be \$31.81.

#
delivery Black/grey water tank
#

rental \$1,329.38 \$625.00/mth. Estimated sales tax would be \$39.69/mth. Black/grey water \$13,825.50 \$6,500.00/mth that includes emptying the tank three times per week. Estimated sales tax would be \$412.75/mth.

#
disposal
#

Project Management \$11,502.80 10 hours/week - \$1,352.00. Estimated sales tax would be \$85.85/week. Daily rate on the hard \$29,097.60 \$456.00/day for yacht to sit out of the water on the hard. Not in the shed. Estimated sales tax would be \$28.96/day.

#
Cooling tower daily
#

rental \$8,627.40 \$135.20/day. Estimated sales tax would be \$8.59/day. Yard forklifts, scissor lift \$525.37 Used to move cooling tower. Estimated sales tax is \$31.37.

#
and crane use Haul and launch 1 x
#

Williams RIB \$829.53 RIB to be removed from garage to facilitate work in the engine room. Estimated sales tax would be \$49.53. Tender storage \$5,574.60 \$87.36/day. Covered storage for tender. Estimated sales tax would be \$5.55/day. Bottom Work Total \$15,013.98 \$0.00 \$0.00 Haulout and Launching BBW \$13,950.48 Synchro lift. Includes naval architect, blocking and divers. Estimated sales tax Pressure wash bottom BBW \$1,063.50 would be \$832.96. Cleaning off of marine growth after haul out. Verbal estimate of \$1,000 provided by BBW. Estimated sales tax would be \$63.50.

#
Deck Total \$12,226.27 \$0.00 \$0.00
#

Bilge boards BBW \$2,425.59 Fabricate bilge boards from white starboard for centre bilge. Estimated cost is \$2,280.76. Estimated sales tax would be \$144.83.

#
Paint repair to starboard
#

bow BBW \$9,800.68 Repair damaged paint fwd of starboard anchor pocket. Estimate is \$9,215.50. Estimated sales tax would be \$585.18.

#
Total Total Quotes \$529,958.79 \$0.00 Total BBW Shipyard Estimates and Quotes Total BBW Shipyard Actual Cost \$529,958.79 \$0.00